Miranda Track Slab Renewal

Project Description
In July 2014 we were engaged by Sydney Trains to support the construction of two track slabs above Kiora Road, Miranda.

  • Survey connection to existing Sydney Trains control
  • Preparation of design alignments and digital terrain modelling (DTM) of the concrete surface
  • Our surveyors were asked to set out core holes for the Delkor Rail Plates, and other tasks included calculating the packing required under the Delkor Plates and the alignment of the rails.

Client: Sydney Trains
Year: July 2014

Back to projects